Notice of Hainan Province on Accelerating the Development of Prefabricated Buildings
By the end of 2022, in the annual commercial housing implementation plan projects of cities and counties, the proportion of prefabricated construction should not be less than 80%. After application and review by the Provincial Department of Housing and Urban-Rural Development to determine projects that meet the national prefabricated building evaluation standards, the project's annual commercial housing plan indicators can be appropriately increased.
1. Strengthen the Management of Approval Process in Each Link of Prefabricated Building
The Provincial Development and Reform Commission, the Provincial Department of Natural Resources and Planning, and the Provincial Department of Housing and Urban-Rural Development should combine their work responsibilities to supervise and implement the closed supervision mechanism for all links of the prefabricated building capital construction procedures. The municipal and county governments should earnestly implement the main responsibility of promoting prefabricated buildings and strengthen the implementation of responsibilities in all links.
In the stage of land transfer, the natural resources planning department shall specify the prefabricated construction method in the land bidding documents for social investment and projects that meet the prefabricated construction conditions. For government-invested projects that meet the prefabricated construction conditions, the development and reform department shall clearly construct the projects in the prefabricated way when the project is approved or the preliminary design budget is approved. (lead units: municipal and county governments, provincial development and Reform Commission, provincial natural resources and Planning Department)
During the planning and construction phase, the natural resources planning department shall review the assembly building section according to the implementation content of the assembly building specified in the land transfer document. (Lead units: municipal and county governments, provincial natural resources and planning departments)
In the construction supervision stage, for projects that meet the construction conditions but do not adopt the assembly method, the main body of supervision should strictly check, and will not accept the construction drawing review, construction permit, completion acceptance application, etc. (Lead unit; each city and county government, provincial housing and urban-rural construction department)
The 2. should strictly control the projects that are not to be built in assembly mode due to technical reasons.
The municipal and county governments shall not decide the construction method of the project in the form of meeting minutes, instructions, instructions, etc. (Lead unit: municipal and county governments).
For projects that are not to be constructed in an assembled manner due to technical reasons, they should be reported to the Provincial Assembly Building Joint Conference Office to organize experts for review and determination. The expert group shall be composed of no less than 7 experts, all of which shall be selected from the Hainan Province prefabricated building expert database. The review must be approved by more than 3/4 experts. (Lead unit: Provincial Department of Housing and Urban-Rural Development)
3. to promote the centralized layout of prefabricated building production bases
Accelerate the promotion of the research and development of technical systems such as prefabricated buildings and green buildings in our province, the production and construction of parts and components, as well as the agglomeration of upstream and downstream industries such as decoration, consulting services, and training, and accelerate the transformation and upgrading of the construction industry in our province. (Lead unit: Provincial Department of Housing and Urban-Rural Development; Cooperating unit: each city and county government)
Coordinate the production capacity layout of assembly-type buildings, in addition to Chengmai, Ding'an, Wanning existing and Sanya proposed assembly-type building industrialization base, the new production capacity of assembly-type building components in principle should be co-ordinated and centralized layout to the Lingao Gold Port Development Zone. (Lead unit: Provincial Department of Housing and Urban-Rural Development; Cooperating unit: relevant city and county governments)
4. to guide the implementation of commercial housing plan projects to use assembly-type construction.
By the end of 2022, in the annual commercial housing implementation plan projects of cities and counties, the proportion of prefabricated construction should not be less than 80%. After application and review by the Provincial Department of Housing and Urban-Rural Development to determine projects that meet the national prefabricated building evaluation standards, the project's annual commercial housing plan indicators can be appropriately increased. (Lead unit: Provincial Department of Housing and Urban-Rural Development; Cooperating unit: each city and county government)
Encourage libraries, exhibition halls, industrial plants, airports, railways, highways, ports and other passenger terminals, office buildings, office buildings, schools, hospitals, parking buildings, and public buildings with a single area of more than 20000 square meters, and seismic fortification intensity 8 The super high-rise buildings in the area are preferentially constructed by steel structures (including steel-concrete composite structures). (Lead unit: each city and county government; cooperating unit: Provincial Development and Reform Commission, Provincial Department of Housing and Urban-Rural Development)
6. encourages municipal bridges and farm house renovation projects to be built in an assembled manner.
Encourage municipal infrastructure such as urban bridges and pipeline corridors to actively use assembly parts. Encourage the renovation of dilapidated houses in rural areas, community activity centers (rooms), police offices and other suitable standardized and modular construction projects to be constructed in an assembled manner. (Lead unit: each city and county government; cooperating unit: Provincial Development and Reform Commission, Provincial Department of Housing and Urban-Rural Development)
7. to promote the application of the general contracting (EPC) model.
In principle, prefabricated construction projects should adopt the general contracting (EPC) model, and consider key links such as design, construction, and production of components. In principle, the bidding stage of EPC shall be started after the approval of project proposal or scheme design is completed. Prefabricated construction projects with an assembly rate of more than 60% and only a small number of potential bidders to choose from may be invited to tender. (Lead unit: municipal and county governments; Cooperating unit: Provincial Department of Housing and Urban-Rural Development)
8. Technology Helps Improve the Quality of Prefabricated Building Products
We will speed up the formulation of standards for assembly building parts, dig deep into the production potential of the existing assembly building parts in our province, and strictly control the quality of assembly building parts. (Lead unit: Provincial Department of Housing and Urban-Rural Development)
Encourage enterprises, institutions of higher learning, and R & D institutions to increase investment in R & D, and carry out technical research on building seismic isolation, anti-corrosion, waterproofing, and shading under strong typhoon, high temperature, high humidity, and high salt conditions. (Lead unit: Provincial Department of Science and Technology; Cooperating unit: Provincial Department of Housing and Urban-Rural Development)
9. highlights assembly building innovation and capacity building
Vigorously promote the technical application of building information modeling (BIM) in the whole life cycle of buildings, such as standards, design, production, construction, operation and maintenance. (Lead unit: Provincial Department of Housing and Urban-Rural Development)
Support enterprises, colleges and universities, and R & D institutions to develop production equipment with a rich variety of products and a high degree of automation, and strengthen support for scientific and technological innovation. (Lead unit: Provincial Department of Science and Technology; Cooperating unit: Provincial Department of Housing and Urban-Rural Development)
Actively introduce design, construction enterprises and scientific research teams with practical experience in the field of assembly construction for the whole country. (Lead unit: Provincial Department of Housing and Urban-Rural Development)
Cultivate a group of talents who are familiar with prefabricated buildings and building information modeling (BIM) technology. Actively promote professional skills training and cultivate a group of assembly construction industry workers. (Lead unit: Provincial Department of Housing and Urban-Rural Development; Cooperating unit: Provincial Department of Human Resources and Social Security)
10. to increase policy support for science and technology industry
For the prefabricated construction industry, it enjoys policy support such as manufacturing, technological innovation, fiscal, taxation and finance in accordance with the relevant regulations of our province's strategic emerging industries. (Lead unit: Provincial Department of Industry and Information Technology; Cooperating unit: Provincial Department of Finance)
Encourage qualified enterprises to actively declare high-tech enterprises and technologically advanced service enterprises in Hainan Province, and enjoy corresponding financial subsidies or preferential tax policies in accordance with regulations. (Lead unit: Provincial Department of Science and Technology; Cooperating unit: Provincial Department of Finance, Provincial Taxation Bureau)
Eleven, speed up the introduction of floor area ratio incentives.
The municipal and county governments should issue and implement the implementation measures for the floor area ratio reward of prefabricated buildings within a time limit to ensure the full implementation of the floor area ratio reward policy stipulated in document 100. For projects under construction or built that meet the floor area ratio incentive policy, the enterprise can apply for the realization of the floor area ratio incentive index in other projects of the enterprise where the project is located. (Lead unit: each city and county government; cooperating unit: Provincial Department of Natural Resources and Planning, Provincial Department of Housing and Urban-Rural Development)
12. Strengthen information exchange and sharing among various departments
The relevant departments of the province, city and county shall share the project information such as project initiation, initial establishment (filing) approval, land transfer, planning permission (filing) and other project information to the member units of the provincial or city and county assembly building joint conference through the government information platform. Housing and urban and rural construction departments at all levels should strengthen the follow-up supervision and technical guidance of the project. (lead units: municipal and county governments, provincial development and Reform Commission; cooperating units: Provincial Department of natural resources and planning, Provincial Department of housing and urban rural development)
XIII. Strengthening regulation and accountability
If the municipal and county governments do not implement the relevant regulations in all aspects of promoting prefabricated construction work, they will be criticized or interviewed. If the circumstances are serious, the new annual commercial housing plan indicators will be stopped. The project construction units, survey and design institutions, drawing review institutions, construction general contracting enterprises and relevant responsible persons who have not performed their responsibilities seriously will be included in the bad credit records and made public. (Leader: Provincial Department of Housing and Urban-Rural Development; Cooperating Unit: Member of the Provincial Joint Conference on the Promotion of Prefabricated Buildings)